BSEB Home Page


Ongoing short and long-term projects

For improvement of transmission and distribution of power in the State of Bihar

Rashtriya Sam-Vikas Yojna: Phase-I (Sub-Transmission Schemes)

SL

Name of Scheme

Total Scope

Present Status

1

220/132 KV GSS

2

Gopalganj: March'2006
Darbhanga: March'2006

2

132/33 KV GSS

15

Bhabhua, Bihta, Sasaram, Barh, Banka, Bikramganj, GSS are availing power.
Vaishali: Control room & Downlinking arrangement under progress. Quarters at GSS yet to be completed.
Jainagar, Dhaka: March,2006
Madhubani: March,2006
Supaul: March, 2006
Sheetalpur: March’2006

3

33/11 KV PSS

1Complete down-linking arrangement under progress.

4

220 KV Line (2 Nos.)

168 Kms

-

5

132 KV Line (19 Nos.)

705 Kms

-

6

33 KV Line (1 Nos.)

43 Kms

-

STRENGTHENING OF TRANSMISSION SYSTEM

New Grids and Lines under RSVY: Phase-I

SL

Name of Scheme

Associated Transmission Line

Remarks

1

132/33 KV
New Bhabhua Substation

LILO of 132 KV Dehri-Karmnasa Line at Bhabhua

Operational.

2

132/33 KV
New Bikramganj Substation

LILO of 132 KV Dehri-Dumraon Line at Bikramganj

Power-Flow started.

3

132/33 KV
New Sasaram Substation

LILO of 132 KV Dehri-Kudra-Karmnasa Line at Sasaram

Load-Flow started.

4

132/33 KV
New Bihta Substation

132 KV Khagaul-Bihta

Operational.

5

132/33 KV
New Banka Substation

132 KV Sabour-Banka

Power-Flow started.

6

132/33 KV
New Barh Substation

LILO of 132 KV Biharsharif-Hathidah Line at Barh

Power-Flow started.

733/11 KV
Banianpur Substation
33KV S/C Siwan-Banianpur Complete. Down-Linking arrangements under progress.
8132/33 KV
New Udakishanganj Substation
132 KV Saharsa-Udakishanganj March'2006.
9132/33 KV
New Jaynagar Substation
132 KV Pandaul-Madhubani-Jaynagar-Phulparas March'2006.
10132/33 KV
New Madhubani Substation
March'2006.
11220/132 KV
Darbhanga Substation
220 KV D/C Muzaffarpur-Darbhanga March'2006.
12132/33
Vaishali Substation
132 KV Muzaffarpur-Vaishali Test charged. Down-Linking arrangements under progress.
13132/33 KV
New Forbesganj Substation
132 KV Kishanganj-Forbesganj-Kataiyaa March'2006.
14132/33 KV
New Sheetalpur Substation
LILO of 132 KV Hajipur-Chapra at Sheetalpur and 132 KV Vaishali-Sheetalpur March'2006.
Land acquisition delayed.
15132/33 KV
Dhaka Substation
132 KV D/C Motihari-Sitamarhi-Dhaka March'2006.
16220/132 KV
Gopalganj Substation
220 KV D/C Muzaffarpur-Gopalganj March'2006.
17132/33 KV
Phulparas Substation
132 KV Phulparas-Supaul-Saharsa March'2006.
18132/33 KV
Supaul Substation
LILO of 132 KV Purnea-Dalkhola at Kishanganj March'2006.

 

Rashtriya Sam-Vikas Yojna: Phase-II (Part 1): Execution to start

  • Estimated Cost : 629.22 Crores

  • Construction of new GSS (i.e. one no. 220/132 KV at Sipara and 6 nos. 132/33KV at Muzaffarpur, Katra, Naugachia, Hulasganj / Ekangarsarai, Buxar & Tekari)

  • Augmentations of capacity by 1170 MVA & R&M of major Grid Sub-Station

  • Capacity augmentation by 1070 MVA at 21 nos. existing GSS

  • Renovation and up-gradation of Protection System of 6 nos. of GSS (i.e.Biharsharif, Baripahari, Bodhgaya, Dehri, Fatuha & Jakkanpur)

  • Completion of remaining works of incomplete GSS at Begusarai and 220 KV DC Begusarai-Purnea Line

  • Reconductoring of 3 nos. of existing lines (i.e. Gaya-Jakkanpur, Begusarai-Samastipur and Barauni-Purnea)

 

Schemes for Distribution

Accelarated Power-Distribution Reform Programme (APDRP) which broadly covers:

  • Up-gradation & Revamping of Distribution System thereby reducing outage and interruption and increasing consumer satisfaction.

  • Installation of New PSS and DSS.

  • Metering thrust to improve billing, reducing commercial losses and achieving commercial viability.

  • Introduction of MIS in Distribution Circles.

  • Re-conductoring of overloaded conductors.

Out of 16 Distribution Circles, 12 covered under APDRP. Rest 4 Distribution Circles, i.e. Bhojpur, Nalanda, Motihari and Samastipur yet to be covered. Schemes under preparation. Total Estimated Cost of schemes amounting to Rs. 866 crores already sanctioned and work under execution.

 

Status of APDRP Schemes up to Jan'2006:

SL

Name of Scheme

Scope

Up to Jan, 2006

1

New 33/11 KV

38 Nos

5 Nos.

2

R&M of 33/11 KV

200 Nos

122 Nos.

3

New 33 KV Line

703 Kms

55 Kms

4

New 11 KV Line

397 Kms

18 Kms

5

Re-conductoring of 33 & 11 KV Line

5,211 Kms

1,890 Kms

6

New DT

1,919 Nos

234 Nos.

7R&M of DT8,666 Set-Nil-
83-Phase Consumer Meter (Powergrid)11,265-Nil-
91-Phase Consumer Meter (Powergrid)2,12,00681,847 supplied
6,000 installed
103-Phase Consumer Meter (BSEB)58,70035,000 inspected
6,000 supplied
111-Phase Consumer Meter (BSEB)2,46,3001,83,490 installed

 

RURAL ELECTRIFICATION SCHEMES

 

Rajiv Gandhi Grameen Vidyutikaran Yojna (RGGVY)

  • All electrified villages (i.e., 20200) are to be extended to provide electricity to all household by 2012 under RGGVY.

  • All un-electrified, de-electrified & partly electrified villages under 30 districts (out of 38 districts) to be electrified by Central Agencies namely PGCIL, NHPC under RGGVY.

  • All un-electrified, de-electrified & partly electrified villages under remaining 8 districts to be electrified by BSEB.

  • PGCIL already started work of village electrification in 5 districts. Work of village electrification in 19 districts to be taken up by the end of March 2006.

  • NHPC likely to start village electrification work in 6 districts by the end of March 2006.

  • Project Report of 4 districts have been submitted to REC. Project Report of 4 districts to be submitted by December 2005. Work likely to be started by 1st April, 2006.

  • On going electrification work in 950 villages and construction of 18 Nos. PSS to be completed during current financial year by BSEB under RE State Plan.