BSEB Home Page


Ongoing short and long-term projects

For improvement of transmission and distribution of power in the State of Bihar


Rashtriya Sam-Vikas Yojna: Phase-II (Part 1): Execution to start


  • Estimated Cost : 629.22 Crores

  • Construction of new GSS (i.e. one no. 220/132 KV at Sipara and 6 nos. 132/33KV at Muzaffarpur, Katra, Naugachia, Hulasganj/Ekangarsarai, Buxar and Tekari).

  • Augmentations of capacity by 1170 MVA & R&M of major Grid Sub-Station.

  • Capacity augmentation by 1070 MVA at 21 nos. existing GSS.

  • Renovation and Up-Gradation of Protection System of 6 nos. of GSS (i.e., Biharsharif, Baripahari, Bodhgaya, Dehri, Fatuha and Jakkanpur).

  • Completion of remaining works of incomplete GSS at Begusarai and 220 KV DC Begusarai-Purnea Line.

  • Reconductoring of 3 nos. of existing lines (i.e., Gaya-Jakkanpur, Begusarai-Samastipur and Barauni-Purnea).


On-Going Works of Grid Sub-Stations under Phase-II (Part-1): RSVY

SL

Name of
Site

Leveling

Work

Control Room
Building

Civil
Works
Structure
Erection
Equipment
Erection

1

Naugachia 132/33 KV G.S.S. Completed In progress In progress In progress -

2

Raxaul 132/33 KV GSS Completed In progress Completed Completed Completed

3

Hulasganj 132/33 KV GSS Completed In progress Completed Completed Completed

4

S.K.M.C.H, Muzaffarpur In progress In progress - - -

5

Ekangarsarai 132/33 KV GSS Completed In progress In progress - -

6

Sipara 220/132/33 KV GSS Acquisition process of land completed. Physical possession of land yet to be had. Revision of compensation amount is under process.

 

Capacity of New Grids under Phase-II (Part-1): RSVY

SL

220/132KV Grids

Capacity

1

Sampat Chak 2 x 150 MVA

2

Begusarai 2 x 100 MVA

 

  Total: 500 MVA

SL

132/33KV Grids

Capacity

1

Katra 2 x 150 MVA

2

Tekari 2 x 20 MVA
3 Naugachhia 2 x 20 MVA
4 Hulashganj 2 x 20 MVA
5 Raxaul 2 x 20 MVA
6 Ekangsarai 2 x 20 MVA
7 S.K.C.M.H. (Muzaffarpur) 2 x 50 MVA
8 Buxar 2 x 20 MVA
9 Begusarai 2 x 50 MVA
    Total: 640 MVA

 

Capacity Augmentation of Old Grids under Phase-II (Part-1): RSVY

SL

220/132KV Grids

Capacity

1

Sheikhpura 1 x 20 MVA

2

Kanti 1 x 100 MVA

 

  Total: 120 MVA

 

Associated Transmission Line (523 Kms) under Phase-II (Part-1): RSVY

SL

Transmission Line

Length

1

LILO of one Circuit of 220 KV D/C Fatuah-Khagaul-Sipara
(Terminated at POWER GRID, Patna)
15.3 ckm

2

132 KV Dehri-Sonenagar 28.9 ckm

3

132 KV Dumraon-Buxar 16.1 ckm

4

132 KV Gaya-Tekari 28.9 ckm
5 132 KV D/C Supaul-Kataiya 118.4 ckm
6 132 KV D/C (S/C Strung) Darbhanga-Phulparas 71.3 ckm
7 LILO of 1st Circuit of 132 KV Fatuha-Gaighat Line 7.2 ckm
8 132 KV S/C (on D/C Tower) Bettiah-Raxaul Line 37.1 ckm
9 132 KV Biharsharif-Hulasganj 44.5 kms
10 LILO of ... Circuit of 132 KV Baxaur-Purnea Line at Naugachia 1.7 ckm
11 LILO of 132 KV, S/C Biharshariff-Hulasganj at Ekarngarsarai 44.5 ckm
12 LILO of S/C Sitamarhi-Muzaffarpur (Ramdayalu Lines) at SKMCH 1.0 ckm
13 132 KV Kant-SKMCH 14.1 ckm
14 LILO of 220 KV Fatuah-Khagaul 18.6 ckm
15 220 KV Power Grid Sipara 0.89 ckm
16 LILO of 2nd Circuit of 132 KV Gaya-Jakkanpur 21.0 km
17 LILO of 132 KV Gaighat-Mithapur Line 20 ckm
18 LILO of 132 KV D/C Baxaur-Samastipur Line at Begusarai 7.7 ckm
19 Stringing of 2nd Circuit of 132 KV D/C Phulparas-Supaul Line 63.8 ckm

 

R&M of Old Grids under Phase-II (Part - 1): RSVY

R&M work on Dehri-on-Sone, Fatuha, Jakkanpur, Barauni, Samastipur has been completed while work at Biharsharif, Bari-Pahari and Bodhgaya is under progress and is expected to be completed shortly. Tender for rest of the Grid Substations is also likely to be finalised.

 

Re-conductoring of Old Lines (362 Kms) under Phase-II (Part-1): RSVY

SL

Transmission Line

Length

1

Chandauti-Jakkanpur 132KV D/C 188.04 ckm

2

Barauni-Khagaria 132KV D/C

3

Purnea-Naugachhia 132KV D/C 70.00 ckm

4

Barauni-Samastipur 132KV D/C

 

On-Going Works of Grid Sub-Stations under Phase-II (Part-2): RSVY

SL

Name of
Site

Leveling

Work

Control Room
Building

Civil
Works
Structure
Erection
Equipment
Erection

1

Dalsingsarai 132/33 KV G.S.S. Completed In progress - - -

2

Goh 132/33 KV G.S.S. Completed In progress - - -

3

Wazirganj 132/33 KV G.S.S. Completed In progress - - -

4

Karpi 132/33 KV G.S.S. Completed In progress - - -

5

Mushrakh 132/33 KV G.S.S. Completed In progress - - -

6

Aurangabad 132/33 KV G.S.S. In Progress In Progress - - -
7 Digha 132/33 KV G.S.S. Land Arranged recently - - - -
8 Haranaut 132/33 KV G.S.S. Land handed over to power grid on 24.09.2009 - - - -
9 Jagdishpur 132/33 KV G.S.S. Completed In progress - - -
10 Hazipur 220/132 KV G.S.S. Tender invited price bid opened in December 2009. - - - -
11 Madhepura 220/132/33 KV G.S.S. Land yet
to be
handed over to PGCIL.
       
12 Kudra 132/33 KV G.S.S.        
13 Dinara 132/33 KV G.S.S.        
14 Kusheshwarsthan 132/33 KV G.S.S.        
15 Runnisaidpur 132/33 KV G.S.S.        
16 Nalanda 132/33 KV G.S.S.        
17 Sonebarsa 132/33 KV G.S.S.        

 

Capacity of New Grids covered under Phase-II (Part-II): RSVY

SL

220/132KV Grids

Capacity

1

Madhepura 2 x 100 MVA

2

Hajipur 2 x 100 MVA

 

  Total: 400 MVA

SL

132/33KV Grids

Capacity

1

Dalsingsarai 2 x 20 MVA

2

Goh 2 x 20 MVA
3 Wazirganj 2 x 20 MVA
4 Karpi 2 x 20 MVA
5 Mushrakh 2 x 20 MVA
6 Aurangabad 2 x 20 MVA
7 Digha 2 x 50 MVA
8 Harnaut 2 x 20 MVA
9 Jagdishpur 2 x 20 MVA
10 Kudra 2 x 20 MVA
11 Dinara 2 x 20 MVA
12 Kusheshwar Asthan 2 x 20 MVA
13 Runnisaidpur 2 x 20 MVA
14 Nalanda 2 x 20 MVA
15 Sonebarsha 2 x 20 MVA
16 Madhepura 2 x 20 MVA
    Total: 700 MVA

 

Associated Transmission Line under Phase-II (Part-2): RSVY

220 KV:136 kms, 132 KV:1,037 kms, 33 KV:340 kms

SL

Transmission Line

Length

1

LILO of Gopalganj-Siwan 132 KV S/C at Mushtrakh

2

Hazipur (old) - Hazipur (new) 132 KV D/C

3

Khagaul-Digha 132 KV D/C

4

Jamui-Sheikhpura 132 KV S/C line on D/C Tower 49 ckm
5 LILO of Bodh Gaya-Nawada 132 KV S/C line at Wajirganj
6 Banjari-Sasaram 132 KV S/C on D/C Tower
7 Dinara-Kudra132 KV S/C line on D/C Tower
8 Biharsharif-Nawada 132 KV S/C line on D/C Tower 41 ckm
9 Biharsharif-Sheikhpura 132 KV S/C line on D/C Tower 39 ckm
10 Stringing of 2nd circuit of Dehri-Dumraon 132 KV Line 90 ckm
11 Begusarai-Kusheshwar Asthan 132 KV S/C on D/C Tower 65 ckm
12 Sonenagar-Aurangabad 132 KV D/C
13 LILO of Dehri-Karmanasa 132 KV S/C (BSEB line) at Kudra
14 Ara (Power grid) - Jagdishpur, 132 KV S/C on D/C Tower 28 ckm
15 Stringing of 2nd circuit of Gopalganj-Bettiah 132 KV D/C 70.7 ckm
16 Purnea (400/220 KV Power grid) - Madhepura-Darbhanga, 220 KV D/C
17 Stringing of 2nd circuit of Samastipur-Chhapra 132 KV Line via Hajipur (new) 107 ckm
18 LILO of SKMCH (Muzaffarpur) - Sitamarhi 132 KV S/C at Runnisaidpur
19 Termination of Hazipur-Muzaffarpur (Kanti) 220 KV D/C line at Muzaffarpur (P.G.)
20 LILO of one circuit of 132 KV D/C Begusarai-Samastipur at Dalsingsarai
21 Jehanabad-Karpi 132 KV S/C line on D/C Tower 22.7 ckm
22 LILO of Bari Pahari-Fatuah Lines at Harnaut
23 Medhepura-Simri-Bakhtiarpur, 132 KV S/C on D/C Tower
24 Tekari-Goh 132 KV S/C on D/C Tower 22.3 ckm
25 132 KV Kahalgaon (NTPC)-Sultanganj-Lakhisarai Line 135 ckm

 

Capacity Augmentation of Existing Substations under Phase-II (Part-2): RSVY

SL

Substations

Capacity

1

Banjari 1 x 20 MVA

2

Katihar 1 x 20 MVA
3 Ramnagar 1 x 20 MVA
4 Lakhisarai 1 x 20 MVA
5 Jamui 1 x 20 MVA
6 Hajipur 1 x 20 MVA
7 Kaliya 1 x 20 MVA
8 Bari Pahari 1 x 50 MVA
9 Hathidah 1 x 20 MVA
10 Khagaul 1 x 100 MVA
11 Dehri 1 x 100 MVA
12 Chapra 1 x 50 MVA

 

  Total: 540 MVA

 

Re-conductoring of Old Lines under Phase-II (Part-2): RSVY

Kahalgaon-Sabour-Sultanganj-Jamalpur-Lakhisarai 132 KV Line and Gaya (Chandauti)-Sonenagar 132 KV D/C Line totalling 180 Kms have been reconduted.

 


RURAL ELECTRIFICATION SCHEMES


Rajiv Gandhi Grameen Vidyutikaran Yojna (RGGVY)

  • All un-electrified & de-electrified villages are to be electrified in 5 years under RGGVY.
  • All electrified villages are to be extended to provide electricity to all household by 2012 under RGGVY.
  • All un-electrified, de-electrified & partly electrified villages under 30 districts(out of 38 districts) to be electrified by Central Agencies namely PGCIL and NHPC under RGGVY.
  • All un-electrified, de-electrified & partly electrified villages under remaining 8 districts to be electrified by BSEB.
  • PGCIL have developed infrastructure in 14332 villages up to July 2009. Out of which 7345 villages have been energized.
  • NHPC have developed infrastructure in 1848 villages up to July 2009. Out of which 870 villages have been energized.
  • In 8 districts BSEB have awarded work to contractors on 29.05.09. The survey-works have been started.
  • Village electrification works are likely to be completed by the end of Dec. 2010.