|
Ongoing short and long-term projects
For improvement of transmission
and distribution of power in the State of Bihar
Rashtriya
Sam-Vikas Yojna: Phase-II (Part 1):
Execution to start
-
Estimated Cost : 629.22 Crores
-
Construction of new GSS (i.e.
one no. 220/132 KV at Sipara and 6 nos. 132/33KV at Muzaffarpur, Katra,
Naugachia, Hulasganj/Ekangarsarai, Buxar and Tekari).
-
Augmentations of capacity
by 1170 MVA & R&M of major Grid Sub-Station.
-
Capacity augmentation by
1070 MVA at 21 nos. existing GSS.
-
Renovation and Up-Gradation
of Protection System of 6 nos. of GSS (i.e., Biharsharif, Baripahari,
Bodhgaya, Dehri, Fatuha and Jakkanpur).
-
Completion of remaining works
of incomplete GSS at Begusarai and 220 KV DC Begusarai-Purnea Line.
-
Reconductoring of 3 nos.
of existing lines (i.e., Gaya-Jakkanpur, Begusarai-Samastipur and Barauni-Purnea).
On-Going
Works of Grid Sub-Stations under Phase-II (Part-1): RSVY
|
SL
|
Name of
Site
|
Leveling
Work
|
Control Room
Building
|
Civil
Works |
Structure
Erection |
Equipment
Erection |
|
1
|
Naugachia 132/33
KV G.S.S. |
Completed |
In
progress |
In
progress |
In
progress |
- |
|
2
|
Raxaul 132/33 KV
GSS |
Completed |
In
progress |
Completed |
Completed |
Completed |
|
3
|
Hulasganj 132/33
KV GSS |
Completed |
In
progress |
Completed |
Completed |
Completed |
|
4
|
S.K.M.C.H,
Muzaffarpur |
In
progress |
In
progress |
- |
- |
- |
|
5
|
Ekangarsarai
132/33 KV GSS |
Completed |
In
progress |
In
progress |
- |
- |
|
6
|
Sipara 220/132/33
KV GSS |
Acquisition process of land completed. Physical possession of land
yet to be had. Revision of compensation amount is under process.
|
Capacity of New Grids under Phase-II (Part-1): RSVY
|
SL
|
220/132KV Grids
|
Capacity
|
|
1
|
Sampat Chak |
2
x 150 MVA |
|
2
|
Begusarai |
2
x 100 MVA |
|
|
|
Total: 500 MVA |
|
SL
|
132/33KV Grids
|
Capacity
|
|
1
|
Katra |
2
x 150 MVA |
|
2
|
Tekari |
2
x 20 MVA |
|
3 |
Naugachhia |
2
x 20 MVA |
|
4 |
Hulashganj |
2
x 20 MVA |
|
5 |
Raxaul |
2
x 20 MVA |
|
6 |
Ekangsarai |
2
x 20 MVA |
|
7 |
S.K.C.M.H.
(Muzaffarpur) |
2
x 50 MVA |
|
8 |
Buxar |
2
x 20 MVA |
|
9 |
Begusarai |
2
x 50 MVA |
|
|
|
Total: 640 MVA |
Capacity Augmentation of Old Grids under Phase-II (Part-1): RSVY
|
SL
|
220/132KV Grids
|
Capacity
|
|
1
|
Sheikhpura |
1
x 20 MVA |
|
2
|
Kanti |
1
x 100 MVA |
|
|
|
Total: 120 MVA |
Associated Transmission Line (523 Kms) under Phase-II (Part-1): RSVY
|
SL
|
Transmission Line
|
Length |
|
1
|
LILO of one
Circuit of 220 KV D/C Fatuah-Khagaul-Sipara
(Terminated at POWER GRID, Patna) |
15.3 ckm |
|
2
|
132 KV
Dehri-Sonenagar |
28.9 ckm |
|
3 |
132
KV Dumraon-Buxar |
16.1 ckm |
|
4
|
132 KV
Gaya-Tekari |
28.9 ckm |
|
5 |
132 KV D/C
Supaul-Kataiya |
118.4 ckm |
|
6 |
132 KV D/C
(S/C Strung) Darbhanga-Phulparas |
71.3 ckm |
|
7 |
LILO of
1st Circuit of 132 KV Fatuha-Gaighat Line |
7.2 ckm |
|
8 |
132 KV S/C
(on D/C Tower) Bettiah-Raxaul Line |
37.1 ckm |
|
9 |
132 KV
Biharsharif-Hulasganj |
44.5 kms |
|
10 |
LILO of
... Circuit of 132 KV Baxaur-Purnea Line at Naugachia |
1.7 ckm |
|
11 |
LILO of
132 KV, S/C Biharshariff-Hulasganj at Ekarngarsarai |
44.5 ckm |
|
12 |
LILO of
S/C Sitamarhi-Muzaffarpur (Ramdayalu Lines) at SKMCH |
1.0 ckm |
|
13 |
132 KV
Kant-SKMCH |
14.1 ckm |
|
14 |
LILO of
220 KV Fatuah-Khagaul |
18.6 ckm |
|
15 |
220 KV
Power Grid Sipara |
0.89 ckm |
|
16 |
LILO of
2nd Circuit of 132 KV Gaya-Jakkanpur |
21.0 km |
|
17 |
LILO of
132 KV Gaighat-Mithapur Line |
20
ckm |
|
18 |
LILO of
132 KV D/C Baxaur-Samastipur Line at Begusarai |
7.7 ckm |
|
19 |
Stringing
of 2nd Circuit of 132 KV D/C Phulparas-Supaul Line |
63.8 ckm |
R&M
of Old Grids under Phase-II (Part - 1): RSVY
R&M work on Dehri-on-Sone,
Fatuha, Jakkanpur, Barauni, Samastipur has been completed while work at
Biharsharif, Bari-Pahari and Bodhgaya is under progress and is expected
to be completed shortly. Tender for rest of the Grid Substations is also
likely to be finalised.
Re-conductoring of Old Lines (362 Kms) under Phase-II (Part-1): RSVY
|
SL
|
Transmission Line
|
Length |
|
1
|
Chandauti-Jakkanpur 132KV D/C |
188.04 ckm |
|
2
|
Barauni-Khagaria
132KV D/C |
|
|
3 |
Purnea-Naugachhia 132KV D/C |
70.00 ckm |
|
4
|
Barauni-Samastipur 132KV D/C |
|
On-Going
Works of Grid Sub-Stations under Phase-II (Part-2): RSVY
|
SL
|
Name of
Site
|
Leveling
Work
|
Control Room
Building
|
Civil
Works |
Structure
Erection |
Equipment
Erection |
|
1
|
Dalsingsarai
132/33 KV G.S.S. |
Completed |
In
progress |
- |
- |
- |
|
2
|
Goh 132/33 KV
G.S.S. |
Completed |
In
progress |
- |
- |
- |
|
3
|
Wazirganj 132/33
KV G.S.S. |
Completed |
In
progress |
- |
- |
- |
|
4
|
Karpi 132/33 KV G.S.S. |
Completed |
In
progress |
- |
- |
- |
|
5
|
Mushrakh
132/33 KV G.S.S. |
Completed |
In
progress |
- |
- |
- |
|
6
|
Aurangabad 132/33
KV G.S.S. |
In Progress |
In Progress |
- |
- |
- |
|
7 |
Digha 132/33 KV
G.S.S. |
Land Arranged recently |
- |
- |
- |
- |
|
8 |
Haranaut 132/33
KV G.S.S. |
Land handed over to power grid on 24.09.2009 |
- |
- |
- |
- |
|
9 |
Jagdishpur 132/33
KV G.S.S. |
Completed |
In progress |
- |
- |
- |
|
10 |
Hazipur 220/132
KV G.S.S. |
Tender invited price bid opened in December 2009. |
- |
- |
- |
- |
|
11 |
Madhepura
220/132/33 KV G.S.S. |
Land yet
to be
handed over to PGCIL. |
|
|
|
|
|
12 |
Kudra 132/33 KV
G.S.S. |
|
|
|
|
|
13 |
Dinara 132/33 KV
G.S.S. |
|
|
|
|
|
14 |
Kusheshwarsthan
132/33 KV G.S.S. |
|
|
|
|
|
15 |
Runnisaidpur
132/33 KV G.S.S. |
|
|
|
|
|
16 |
Nalanda 132/33 KV
G.S.S. |
|
|
|
|
|
17 |
Sonebarsa 132/33
KV G.S.S. |
|
|
|
|
Capacity of New Grids covered under Phase-II (Part-II): RSVY
|
SL
|
220/132KV Grids
|
Capacity
|
|
1
|
Madhepura |
2
x 100 MVA |
|
2
|
Hajipur |
2
x 100 MVA |
|
|
|
Total: 400 MVA |
|
SL
|
132/33KV Grids
|
Capacity
|
|
1
|
Dalsingsarai |
2
x 20 MVA |
|
2
|
Goh |
2
x 20 MVA |
|
3 |
Wazirganj |
2
x 20 MVA |
|
4 |
Karpi |
2
x 20 MVA |
|
5 |
Mushrakh |
2
x 20 MVA |
|
6 |
Aurangabad |
2
x 20 MVA |
|
7 |
Digha |
2
x 50 MVA |
|
8 |
Harnaut |
2
x 20 MVA |
|
9 |
Jagdishpur |
2
x 20 MVA |
|
10 |
Kudra |
2
x 20 MVA |
|
11 |
Dinara |
2
x 20 MVA |
|
12 |
Kusheshwar
Asthan |
2
x 20 MVA |
|
13 |
Runnisaidpur |
2
x 20 MVA |
|
14 |
Nalanda |
2
x 20 MVA |
|
15 |
Sonebarsha |
2
x 20 MVA |
|
16 |
Madhepura |
2
x 20 MVA |
|
|
|
Total: 700 MVA |
Associated Transmission Line under Phase-II (Part-2): RSVY
220 KV:136 kms, 132 KV:1,037 kms, 33 KV:340 kms
|
SL
|
Transmission Line
|
Length |
|
1
|
LILO of
Gopalganj-Siwan 132 KV S/C at Mushtrakh |
|
|
2
|
Hazipur (old) -
Hazipur (new) 132 KV D/C |
|
|
3 |
Khagaul-Digha 132 KV D/C |
|
|
4
|
Jamui-Sheikhpura 132 KV S/C line on D/C Tower |
49 ckm |
|
5 |
LILO of
Bodh Gaya-Nawada 132 KV S/C line at Wajirganj |
|
|
6 |
Banjari-Sasaram 132 KV S/C on D/C Tower |
|
|
7 |
Dinara-Kudra132 KV S/C line on D/C Tower |
|
|
8 |
Biharsharif-Nawada 132 KV S/C line on D/C Tower |
41 ckm |
|
9 |
Biharsharif-Sheikhpura 132 KV S/C line on D/C Tower |
39 ckm |
|
10 |
Stringing
of 2nd circuit of Dehri-Dumraon 132 KV Line |
90 ckm |
|
11 |
Begusarai-Kusheshwar Asthan 132 KV S/C on D/C Tower |
65 ckm |
|
12 |
Sonenagar-Aurangabad
132 KV D/C |
|
|
13 |
LILO of
Dehri-Karmanasa 132 KV S/C (BSEB line) at Kudra |
|
|
14 |
Ara (Power
grid) - Jagdishpur, 132 KV S/C on D/C Tower |
28 ckm |
|
15 |
Stringing
of 2nd circuit of Gopalganj-Bettiah 132 KV D/C |
70.7 ckm |
|
16 |
Purnea
(400/220 KV Power grid) - Madhepura-Darbhanga, 220 KV D/C |
|
|
17 |
Stringing
of 2nd circuit of Samastipur-Chhapra 132 KV Line via Hajipur
(new) |
107 ckm |
|
18 |
LILO of
SKMCH (Muzaffarpur) - Sitamarhi 132 KV S/C at Runnisaidpur |
|
|
19 |
Termination of Hazipur-Muzaffarpur (Kanti) 220 KV D/C line at
Muzaffarpur (P.G.) |
|
|
20 |
LILO of
one circuit of 132 KV D/C Begusarai-Samastipur at Dalsingsarai |
|
|
21 |
Jehanabad-Karpi 132 KV S/C line on D/C Tower |
22.7 ckm |
|
22 |
LILO of
Bari Pahari-Fatuah Lines at Harnaut |
|
|
23 |
Medhepura-Simri-Bakhtiarpur, 132 KV S/C on D/C Tower |
|
|
24 |
Tekari-Goh
132 KV S/C on D/C Tower |
22.3 ckm |
|
25 |
132 KV
Kahalgaon (NTPC)-Sultanganj-Lakhisarai Line |
135 ckm |
Capacity Augmentation of Existing Substations under Phase-II (Part-2): RSVY
|
SL
|
Substations
|
Capacity
|
|
1
|
Banjari |
1
x 20 MVA |
|
2
|
Katihar |
1
x 20 MVA |
|
3 |
Ramnagar |
1
x 20 MVA |
|
4 |
Lakhisarai |
1
x 20 MVA |
|
5 |
Jamui |
1
x 20 MVA |
|
6 |
Hajipur |
1
x 20 MVA |
|
7 |
Kaliya |
1
x 20 MVA |
|
8 |
Bari Pahari |
1
x 50 MVA |
|
9 |
Hathidah |
1
x 20 MVA |
|
10 |
Khagaul |
1
x 100 MVA |
|
11 |
Dehri |
1
x 100 MVA |
|
12 |
Chapra |
1
x 50 MVA |
|
|
|
Total: 540 MVA |
Re-conductoring of Old Lines under Phase-II (Part-2): RSVY
Kahalgaon-Sabour-Sultanganj-Jamalpur-Lakhisarai 132 KV Line and Gaya (Chandauti)-Sonenagar
132 KV D/C Line totalling 180 Kms have been reconduted.
RURAL ELECTRIFICATION SCHEMES
Rajiv
Gandhi Grameen Vidyutikaran Yojna (RGGVY)
- All un-electrified & de-electrified villages are to be electrified
in 5 years under RGGVY.
- All electrified villages are to be extended to provide electricity
to all household by 2012 under RGGVY.
- All un-electrified, de-electrified & partly electrified villages
under 30 districts(out of 38 districts) to be electrified by Central
Agencies namely PGCIL and NHPC under RGGVY.
- All un-electrified, de-electrified & partly electrified villages
under remaining 8 districts to be electrified by BSEB.
- PGCIL have developed infrastructure in 14332 villages up to July
2009. Out of which 7345 villages have been energized.
- NHPC have developed infrastructure in 1848 villages up to July 2009.
Out of which 870 villages have been energized.
- In 8 districts BSEB have awarded work to contractors on 29.05.09.
The survey-works have been started.
- Village electrification works are likely to be completed by the
end of Dec. 2010.
|