| | Ongoing short and long-term projects
For improvement of transmission and distribution of power in the State of Bihar
Rashtriya Sam-Vikas Yojna: Phase-I (Sub-Transmission Schemes) SL |
Name of Scheme | Total Scope |
Present Status |
1 | 220/132 KV GSS |
2 |
Gopalganj: March'2006
Darbhanga: March'2006 | 2 | 132/33 KV GSS |
15 | Bhabhua, Bihta, Sasaram, Barh, Banka, Bikramganj, GSS are availing power.
Vaishali: Control room & Downlinking arrangement under progress. Quarters at GSS yet to be completed.
Jainagar, Dhaka: March,2006
Madhubani: March,2006
Supaul: March, 2006
Sheetalpur: March’2006 | 3 |
33/11 KV PSS | 1 | Complete down-linking arrangement under progress. | 4 |
220 KV Line (2 Nos.) |
168 Kms |
- | 5 |
132 KV Line (19 Nos.) |
705 Kms | - | 6 |
33 KV Line (1 Nos.) |
43 Kms | - |
STRENGTHENING OF TRANSMISSION SYSTEM
New Grids and Lines under RSVY: Phase-I
SL |
Name of Scheme | Associated Transmission Line |
Remarks |
1 | 132/33 KV
New Bhabhua Substation |
LILO of 132 KV Dehri-Karmnasa Line at Bhabhua |
Operational. | 2 |
132/33 KV
New Bikramganj Substation |
LILO of 132 KV Dehri-Dumraon Line at Bikramganj |
Power-Flow started. | 3 |
132/33 KV
New Sasaram Substation | LILO of 132 KV Dehri-Kudra-Karmnasa Line at Sasaram |
Load-Flow started. | 4 |
132/33 KV
New Bihta Substation |
132 KV Khagaul-Bihta |
Operational. | 5 |
132/33 KV
New Banka Substation |
132 KV Sabour-Banka |
Power-Flow started. | 6 |
132/33 KV
New Barh Substation |
LILO of 132 KV Biharsharif-Hathidah Line at Barh |
Power-Flow started. | | 7 | 33/11 KV
Banianpur Substation |
33KV S/C Siwan-Banianpur |
Complete. Down-Linking arrangements under progress. | | 8 | 132/33 KV
New Udakishanganj Substation |
132 KV Saharsa-Udakishanganj |
March'2006. | | 9 | 132/33 KV
New Jaynagar Substation |
132 KV Pandaul-Madhubani-Jaynagar-Phulparas |
March'2006. | | 10 | 132/33 KV
New Madhubani Substation |
|
March'2006. | | 11 | 220/132 KV
Darbhanga Substation |
220 KV D/C Muzaffarpur-Darbhanga |
March'2006. | | 12 | 132/33
Vaishali Substation |
132 KV Muzaffarpur-Vaishali |
Test charged. Down-Linking arrangements under progress. | | 13 | 132/33 KV
New Forbesganj Substation |
132 KV Kishanganj-Forbesganj-Kataiyaa |
March'2006. | | 14 | 132/33 KV
New Sheetalpur Substation |
LILO of 132 KV Hajipur-Chapra at Sheetalpur and 132 KV Vaishali-Sheetalpur |
March'2006.
Land acquisition delayed. | | 15 | 132/33 KV
Dhaka Substation |
132 KV D/C Motihari-Sitamarhi-Dhaka |
March'2006. | | 16 | 220/132 KV
Gopalganj Substation |
220 KV D/C Muzaffarpur-Gopalganj |
March'2006. | | 17 | 132/33 KV
Phulparas Substation |
132 KV Phulparas-Supaul-Saharsa |
March'2006. | | 18 | 132/33 KV
Supaul Substation |
LILO of 132 KV Purnea-Dalkhola at Kishanganj |
March'2006. |
Rashtriya Sam-Vikas Yojna: Phase-II (Part 1): Execution to start
-
Estimated Cost : 629.22 Crores
-
Construction of new GSS (i.e. one no. 220/132 KV at Sipara and 6 nos. 132/33KV at Muzaffarpur, Katra, Naugachia, Hulasganj / Ekangarsarai, Buxar & Tekari)
-
Augmentations of capacity by 1170 MVA & R&M of major Grid Sub-Station
-
Capacity augmentation by 1070 MVA at 21 nos. existing GSS
-
Renovation and up-gradation of Protection System of 6 nos. of GSS (i.e.Biharsharif, Baripahari, Bodhgaya, Dehri, Fatuha & Jakkanpur)
-
Completion of remaining works of incomplete GSS at Begusarai and 220 KV DC Begusarai-Purnea Line
-
Reconductoring of 3 nos. of existing lines (i.e. Gaya-Jakkanpur, Begusarai-Samastipur and Barauni-Purnea)
Schemes for Distribution
Accelarated Power-Distribution Reform Programme (APDRP) which broadly covers:
-
Up-gradation & Revamping of Distribution System thereby reducing outage and interruption and increasing consumer satisfaction.
-
Installation of New PSS and DSS.
-
Metering thrust to improve billing, reducing commercial losses and achieving commercial viability.
-
Introduction of MIS in Distribution Circles.
-
Re-conductoring of overloaded conductors.
Out of 16 Distribution Circles, 12 covered under APDRP. Rest 4 Distribution Circles, i.e. Bhojpur, Nalanda, Motihari and Samastipur yet to be covered. Schemes under preparation. Total Estimated Cost of schemes amounting to Rs. 866 crores already sanctioned and work under execution.
Status of APDRP Schemes up to Jan'2006:
SL |
Name of Scheme | Scope |
Up to Jan, 2006 |
1 | New 33/11 KV |
38 Nos |
5 Nos. | 2 |
R&M of 33/11 KV |
200 Nos |
122 Nos. | 3 |
New 33 KV Line |
703 Kms |
55 Kms | 4 |
New 11 KV Line |
397 Kms |
18 Kms | 5 |
Re-conductoring of 33 & 11 KV Line |
5,211 Kms |
1,890 Kms | 6 |
New DT |
1,919 Nos | 234 Nos. | | 7 | R&M of DT | 8,666 Set | -Nil- | | 8 | 3-Phase Consumer Meter (Powergrid) | 11,265 | -Nil- | | 9 | 1-Phase Consumer Meter (Powergrid) | 2,12,006 | 81,847 supplied
6,000 installed | | 10 | 3-Phase Consumer Meter (BSEB) | 58,700 | 35,000 inspected
6,000 supplied | | 11 | 1-Phase Consumer Meter (BSEB) | 2,46,300 | 1,83,490 installed |
RURAL ELECTRIFICATION SCHEMES
Rajiv Gandhi Grameen Vidyutikaran Yojna (RGGVY)
All electrified villages (i.e., 20200) are to be extended to provide electricity to all household by 2012 under RGGVY.
All un-electrified, de-electrified & partly electrified villages under 30 districts (out of 38 districts) to be electrified by Central Agencies namely PGCIL, NHPC under RGGVY.
All un-electrified, de-electrified & partly electrified villages under remaining 8 districts to be electrified by BSEB.
PGCIL already started work of village electrification in 5 districts. Work of village electrification in 19 districts to be taken up by the end of March 2006.
NHPC likely to start village electrification work in 6 districts by the end of March 2006.
Project Report of 4 districts have been submitted to REC. Project Report of 4 districts to be submitted by December 2005. Work likely to be started by 1st April, 2006.
On going electrification work in 950 villages and construction of 18 Nos. PSS to be completed during current financial year by BSEB under RE State Plan.
|
|  |