New Projects To help improve power generation capability, some new projects are already being processed by the Bihar State Electricity Boards. They are as follows - Muzaffarpur Thermal Project
Nabi Nagar Thermal Power Station
Bihata Thermal Power Station
Katihar Thermal Power Station
Patna
Gas Turbine Station
A brief summary of plans for these projects appear here -
SL |
New Projects |
Capacity |
Total
Capacity |
Estimated Project Cost (in Crores) | 1. |
Muzaffarpur TPS Ext Stage-I |
2x250 MW | 500 MW |
2,250.00 |
2. |
Muzaffarpur TPS Ext Stage-II |
1x250 MW |
250 MW |
1,100.00 |
3. |
Nabi Nagar TPS |
4x500 MW |
2000 MW |
8,000.00 |
4. |
Katihar TPS |
2x250 MW |
500 MW |
2,250.00 |
| 5. | Bihta TPS |
2x67.5 MW |
130 MW |
580.00 |
| 6. | CC Gas Power Plant
Phase-I |
1x400 MW |
400 MW |
1,600.00 |
| 7. | CC Gas Power Plant
Phase-II |
1x400 MW |
400 MW |
1,600.00 |
| |
Total |
|
4,180 MW |
17,380.00 |
There is a proposal for installation of two nos. 2x250 MW thermal units in the
extension Stage-I at Muzaffarpur (MTPS). The CEA has accorded techno-economic
clearance for this project in May’93 and Planning Commission also accorded
approval in 1995 at an estimated cost of Rs. 1452.13 crores. But the
construction work of this project could not start as yet due to non-availability
of fund. The present day estimated cost has gone to Rs.2250 crores. On
availability of fund, the project is likely to commence by end of 10th Plan and
to be completed in 11th plan.
This plant will be a boon for Bihar especially for North-Bihar
region. This place is situated on the North side of Ganga at a Latitude of
26º-11'-30" North and longitude 85º-11'-00" East. It is situated on NH-28 and is
on East Central Railway.
There is also a proposal to install one unit of 250 MW in its
extension Stage-II.
Details of Key Clearance:
SL |
Item |
Action Taken |
Action to be Taken | 1. |
Techno-Economic clearance of CEA |
DPR submitted in 1989.
Supplement DPR submitted in May 1990. CEA accorded approval in 1993. |
To be revalidated. |
2. |
Planning Commission |
Accorded approval in
Dec'1995. |
To obtain a fresh approval. |
3. |
Land |
Available at MTPS. |
- |
4. |
Publication under Article-29 |
Published. |
- |
| 5. | Water availability |
Available (Tube-Wells/Canal) |
To obtain permission afresh. |
| 6. | State Pollution Control
Board |
NOC obtained in the year
1991. |
To be revalidated. |
| 7. | Forest Clearance |
- |
To be obtained. |
| 8. | Civil Aviation |
Obtained. |
To be revalidated. |
| 9. | Fuel Linkage |
- |
To be taken afresh. |
| 10. | GOI, Environment and
Forest Clearance | Obtained in 1990 which was
re-obtained in 1992 for 200M height. |
To be revalidated. |
| 11. | National Airport
Authority Clearance | Obtained in 1991. |
To be revalidated. |
This is one of the Mega Project of capacity 4x500MW= 2000MW at an estimated cost of Rs. 8000 Cr. This place is situated in Aurangabad district at Latitude of 24°-43'-48"
North and Longitude 84°-05'-36" East. This is an eastern Railway Section between Dehri-on-Sone Barwadih Rail Links. The Commissioning of this project will be a boon for this state, which is running under acute power crisis. Availability of fund is a bottleneck for starting this project.
Details of Key Clearance:
SL |
Item |
Action Taken |
Action to be Taken | 1. |
Techno-Economic clearance of CEA |
DPR submitted in 1989 but the
same was returned due to non tie-up of essential inputs. |
To be obtained afresh. |
2. |
Planning Commission |
- |
To be obtained. |
3. |
In principal Land
availability clearance |
Land identified. |
Further action to be taken for land
acquisition. |
4. |
Publication |
Published in Aug'1998. |
- |
| 5. | Water availability |
GOB agreed to supply full
quantity of water from Sone river in April'1992. |
To be revalidated. |
| 6. | Fuel availability |
Ministry of Coal agreed to supply 7.2MT per
year from North Karanpura Coal Field in May'1990. |
To be revalidated. |
| 7. | Pollution Clearance |
Obtained from GOB in 1991. |
To be revalidated. |
| 8. | Forest Clearance |
GOB accorded formal clearance
and requested GOI, MOE&F for according clearance in 1989. |
To be obtained afresh. |
| 9. | Civil Aviation |
NOC obtained from National Airport Authority,
New Delhi in 1990 for chimney height of 275M. |
To be revalidated. |
| 10. | Defense Clearance |
- |
To be obtained. |
Bihta is near to Patna. It is about 30 Km from Patna on Latitude of 25°-31'-30"
North and longitude of 84°-51'-00" East. It is on Patna-Muzaffarpur Rail section of Central Eastern Rly. There is a proposal of two units of 2 x 67.5 MW at Bihta. Here the unit capacity is restricted due to military air base, which restricts the chimney height.
Details of Key Clearance:
SL |
Item |
Action Taken |
Action to be Taken | 1. |
Techno-Economic clearance of CEA |
DPR submitted in 1990. |
To be obtained afresh. |
2. |
Planning Commission |
- |
To be obtained. |
3. |
Land availability |
550 acres of land identified. |
Further action to be taken for land
acquisition. |
4. |
Publication |
Published. |
- |
| 5. | Water availability |
Obtained from both GOB and
GOI. |
To be revalidated. |
| 6. | Fuel availability |
Obtained. |
To be revalidated. |
| 7. | Pollution Clearance |
Obtained. |
To be revalidated. |
| 8. | Forest Clearance |
Obtained. |
To be revalidated. |
| 9. | Civil Aviation |
NOC obtained. |
To be revalidated. |
| 10. | Defense Clearance |
- |
To be obtained. |
Katihar is an important industrial town of north Bihar. This place is mainly known for Jute, Plywood and food processing unit. The location is at an latitude of 25°-25'
North and longitude of 87°-15' East. There is a proposal of two unit of 250 MW with total capacity 500MW. The estimated cost of this project is 2250 crores.
Details of Key Clearance:
SL |
Item |
Action Taken |
Action to be Taken | 1. |
Techno-Economic clearance of CEA |
DPR submitted in Dec'1993 but the
same was returned due to non tie-up of essential inputs. |
To be obtained afresh. |
2. |
Planning Commission |
Not obtained. |
To be obtained. |
3. |
Land
availability |
1,018 Hectare Land identified. |
Further action to be taken for land
acquisition. |
4. |
Publication |
Published. |
- |
| 5. | Water availability |
Under process. |
To be revalidated. |
| 6. | Fuel availability |
Expected from Raj Mahal/Jharia/Assam Coal
Fields. |
To be revalidated. |
| 7. | Pollution Clearance |
Under process. |
To be revalidated. |
| 8. | Forest Clearance and
Environment Clearance from State Govt. |
Obtained. |
To be revalidated. |
| 9. | Forest Clearance from MOE
and GOI |
No Forest Land is involved. |
To be revalidated. |
| 10. | Civil Aviation Clearance |
Obtained. |
To be revalidated. |
| 11. | Defense Clearance |
- |
To be obtained. |
Patna Gas
based Power Plant |
The state Government has a proposal to set up gas based plant in and around Patna. Feasibility report for setting up of two-multi fuel gas turbine is under preparation. There is a proposal for two phase of 400 MW each totaling to 800MW. This will be the first of its kind in Bihar, which will run on gas. In this regard, Gas Authority of India has agreed to supply gas for this project. The probable site for this plant is to be located. |